Bradford Water Pollution Control Plant

Project Description

The objective of the Bradford Water Pollution Control Plant (WPCP) upgrades projects is to address the plant's operational requirements and ensure that there is adequate wastewater treatment capacity to service growth to 2031 and beyond. There are two ongoing WPCP upgrade projects.

1: WPCP Critical Upgrades Project

Plant state of good repair analysis, process optimization study and upgrades validation. Design and construction for upgrades to the plant headworks building, chemical/ odour control systems and a new sludge thickening system. These upgrades are implemented under three construction projects

i. WPCP Headworks Upgrades project will replace the headworks building's odour control system

Key Dates:

Design

2021-2023

Construction

2025-2026

ii. WPCP Optimization Upgrades project will replace Plant D’s aeration system

Key Dates:

Design

2022-2024

Construction

2025-2027

iii. WPCP Biosolids Upgrades project for the construction of a new sludge thickening facility

Key Dates:

Design

2022-2024

Construction

2024-2028


2. WPCP Tertiary System Upgrade Project

Design and construction of a new tertiary (membrane) treatment facility for the WPCP

Key Dates:

​Design

2020-2024

​Construction

2025-2028

Contact Us

Town of Bradford West Gwillimbury
100 Dissette St., Unit 7&8
Bradford, ON, L3Z 2A7

Phone: 905-775-5366

Sign up to our Newsletter

Stay up to date on the city's activities, events, programs and operations by subscribing to our eNewsletters.